• Home
  • Electrical Switchboards
  • Testing & Commissioning
  • Engineering Services
  • Contact Us
  • Home
  • Electrical Switchboards
  • Testing & Commissioning
  • Engineering Services
  • Contact Us

  • Home
  • 1 July 2023
  • Electrical Switchboard Manufacturer | Technical Articles

Primary Injection Testing of CTs and VTs

Primary injection testing entails applying a known amount of electrical voltage or current directly to the primary side of a CT or VT. This replicates real operating conditions and enables the technician to test the performance of the transformer, wiring, and protection devices attached as an integrated entity.

For CTs, this means injecting high currents—often in the hundreds or thousands of amperes—into the primary conductor. For VTs, the test involves applying a high voltage to the primary winding and observing the output on the secondary side. By doing this, you’re able to check if the transformer ratio is accurate, if the polarity is correct, and if the protection relay downstream will respond as expected during a real event.

In contrast to secondary injection, which merely tests the relay or meter input only, primary injection simulates the entire system response. This is essential during commissioning or after significant electrical upgrades.

Why Primary Injection Testing Is Important

Primary injection testing is particularly critical in installations where protection systems have to run dependably during faults. Whether a medium-voltage switchboard in a commercial facility or a substation supplying an industrial complex, ensuring protection relays respond properly is critical to safety, compliance, and availability.

In Australian practice, DNSPs (Distribution Network Service Providers) will usually insist that CTs and VTs, particularly those intended for metering or protection, are tested under representative conditions. Although there are recognised tolerances for the accuracy of CTs and VTs, site conditions—cabling losses, bad terminations, or miswiring, for example—can result in inaccurate measurements. Primary injection enables these to be picked up early.

That’s where it truly comes into its own:

You can check that CT polarity is proper prior to energizing a feeder.

You can check that VTs are putting the appropriate voltage on to meters or relays.

You can test fault conditions to confirm protection relay trip points and timing.

You can detect wiring faults, misconfigured ratio settings, or saturated CTs.

How It Works with CTs

Let us begin with current transformers. Current transformers, or CTs, are intended to transform high primary currents into measurable secondary currents—typically 1 A or 5 A. The accuracy and response of the CT are important for both metering and protection.

On a primary injection test, a portable test set injects current through the CT primary side. This may be the real busbar, a conductor, or a cable taken through the CT core. The injected current is measured and controlled carefully. At the same time, the secondary side output is measured and compared against the measured value for the expected value on the basis of the CT ratio.

You’re not only measuring a proper ratio—you’re also testing for:

Correct polarity (so as not to cause relay malfunction)

Phase angle error (which affects differential protection)

Saturation behavior, particularly for protection-grade CTs

For instance, if a 1000:5 ratio CT is supplied with a 1000 A primary injection, its secondary current must be 5 A. If lower, you may have a shorted winding or improper burden.

What About VTs?

Voltage transformers, or potential transformers, work on the same fundamental principle as CTs but step down voltage rather than current. They play an essential role in overvoltage and undervoltage protection, synchronisation, and metering applications.

In a primary injection test for a VT, the VT’s primary winding is connected to a high voltage source. For practical and safety purposes, the voltages are frequently less than the rated voltage but adequate to support transformer capability verification. The secondary output is afterward analyzed and compared with the scaled value as expected.

This test verifies:

The VT ratio

Polarity and phase relationships

Correct delivery of voltage to attached devices

Winding integrity

Again, it’s not simply a matter of a number. It’s about verifying that the whole voltage signal path from source to relay or meter is accurate and error-free.

Equipment Used in Primary Injection Testing

Primary injection testing is not something you accomplish with a multimeter and a clipboard. It needs specialized, high-power equipment capable of providing large, controlled current or voltage outputs in a safe manner.

Typical equipment includes

State-of-the-art injection test sets with the ability to output up to 10,000 A for CT testing

High-voltage injection units to supply high, accurate voltages for VT testing

Measurement probes and data recorders for monitoring secondary output and checking timing

New testers also include onboard software for automatic reporting, ratio checking, and relay coordination testing.

It is interesting that Australian test engineers tend to work under strict electrical safety standards, such as isolation of circuits, lockout/tagout protocols, and personal protective gear. These aren’t good practice—these are requirements.

When and Where It’s Done

Primary injection testing is typically done during:

Commissioning of new substations, switchboards, or transformer installations

Upgrade or modification of existing protection systems

Periodic maintenance on key assets such as generators, feeders, or transformers

You’ll also find it used when issues arise, such as unexplained relay trips or apparent metering discrepancies. Because it evaluates the whole system, primary injection testing is the fastest way to get a definitive answer about whether the CT or VT is to blame.

Limitations and Challenges

Though first-injection testing is worth its weight in gold, it’s not without difficulties. It can be expensive and bulky equipment. You must have trained staff to safely execute the test and read the test results correctly. Above all, you usually have to de-energise the system first—sometimes necessitating planned outages or liaison with the network operator.

Nevertheless, these constraints are greatly overshadowed by the advantages. There is no other test that provides you with this level of assurance that your protection and metering systems are performing just as they should.

We design and manufacture high-quality switchboards. Contact us today to discuss your requirements and get started!

Tags: Electrical Engineering
Electrical Switchboard Manufacturer
  • BESS & Batteries
  • Electric Vehicles & EV Charging Switchboards
  • Electrical Enclosures
  • Engineering Resources
  • High & Medium Voltage
  • Integrating Diesel & Backup Generation
  • Power Quality Analysis
  • Protection Relays & Injection Testing
  • Renewable Energy & Power Generation
  • Solar Standards: AS/NZS 4777 2024
  • Switchboards & Components
  • Virtual Power Plants & Smart Grids
  • Wiring Rules AS/NZS 3000
  • electrical switchboard | electrical switchboards
    What is Edge Computing? How it helps power distribution?
    Edge computing refers to an arrangement where data processing occurs… Read more: What is Edge Computing? How it helps power distribution?
  • electrical switchboard | electrical switchboards
    What is Net Zero Building? How it uses Smart Switchboards?
    Net Zero building is designed in a way that allows… Read more: What is Net Zero Building? How it uses Smart Switchboards?
  • electrical switchboard | electrical switchboards
    What is Paralleling Switchgear? How it works?
    Paralleling switchgear is basically a low-voltage switchboard used to control… Read more: What is Paralleling Switchgear? How it works?
  • electrical switchboard | electrical switchboards
    What is Electrification? Understanding the Basics
    Electrification is turning into one of the major trends in… Read more: What is Electrification? Understanding the Basics
  • What is a Data Center?
    What Is a Data Center? Discover How it works!
    DATA CENTER – Each day, we use the internet and… Read more: What Is a Data Center? Discover How it works!
  • 250A Chassis
    Understanding a 250A Chassis in a Distribution Board
    A 250A chassis is an example of a type of… Read more: Understanding a 250A Chassis in a Distribution Board
  • arc flash protection
    Arc Flash Protection – What Really Happens When Systems Fail
    The technician didn’t hear anything unusual. No alarm. No warning.… Read more: Arc Flash Protection – What Really Happens When Systems Fail
  • Do All Switchboards Require a Dedicated Room?
    Do All Switchboards Require a Dedicated Room?
    Switchboards are usually mounted on a garage wall, sometimes in… Read more: Do All Switchboards Require a Dedicated Room?
  • Is SMA leaving the Australian market?
    Why is SMA shutting down in Australia? Explained!
    Is SMA really going to close down? SMA’s move in… Read more: Why is SMA shutting down in Australia? Explained!
  • electrical switchboard | electrical switchboards
    What Are Electronic Overload Relays? Explained!
    Electronic overload relay sends a signal to the contactor to… Read more: What Are Electronic Overload Relays? Explained!
  • electrical switchboard | electrical switchboards
    AS/NZS 3000 Switchboard Rules – Complete Guide for Compliance and Safety
    Switchboard rules is critical for ensuring electrical safety and functionality.… Read more: AS/NZS 3000 Switchboard Rules – Complete Guide for Compliance and Safety
  • electrical switchboard | electrical switchboards
    AS/NZS 3000 Switchboard Clearances: Safety Rules Every Electrician Must Know
    Ensuring proper switchboard clearances is crucial for maintaining safety and… Read more: AS/NZS 3000 Switchboard Clearances: Safety Rules Every Electrician Must Know

Contact Us

Phone: 02 9558 2480

Email: contact@cleantechcontrols.com.au

Sales (VIC) 0435 812 094

Sales (NSW) 0405 352 840

Sales (WA) 0419 423 609

Useful Links

  • Home
  • Electrical Switchboards
  • Injection Testing & PQA
  • Engineering Services
  • Technical Articles
  • About Us
  • Contact Us
© 2020 Clean Technology Controls. All Rights Reserved.